LAO Team Weekly Status Report

 
 
Week's Activities | Issues Addressed | Next Week's Goals | Next Week's Meeting | Remarks/Concerns
 
Date February 28, 2003  
Prepared By Marcella Simon  
Week's Activities

Our team met to discuss the following:

  • Strategy and plans for usability testing
  • Usability subgroup updates
  • Review of personas

 

top
Issues Addressed
Issues Action to be Taken Due Date
usability testing logistics, materials, planning, roles prepare for dry run on Thursday and dyads on Friday 2/27/03
  revisions of protocol, materials, and methods based on dry run 2/18/03

 

top
Next Week's Goals

Our goals for next week

  • Continue usability tests
  • Review and debrief results
  • Decide on next steps

 

top
Next Week's Meeting

Our next meeting will be held on Thursday March 6 at 1:30 PM in Commerce. The following team members will fill the capacity of

Facilitator: Marcella
Scribe: Lisa
Status Reporter: Lisa
Timekeeper:  

 

top
Remarks/ Concerns

The following concerns need to be addressed

  • Results of uasbility tests
  • Progress on usability tests
  • Final personas

 

top