LAO Team Weekly Status Report

 
 
Week's Activities | Issues Addressed | Next Week's Goals | Next Week's Meeting | Remarks/Concerns
 
Date January 27 through January 31  
Prepared By Peter Huffer  
Week's Activities

Our team met to discuss the following:

  • Complete vision, mission, goals statement
  • Project site information
  • Preparation of questions for Mike Behrman, Seunghun Ok
  • Lisa presented project management calendar
  • Go-around of ideas for project
  • Preliminary project planning
top
Issues Addressed
Issues Action to be Taken Deliverable Owner Due Date
Vision, mission, goals Publish on project site document for website Rob ASAP
Direction for project Research and interviews report due to Steve team Friday, Feb. 7
Performance Analysis Research and interview report due to Rob team This week
Performance Analysis Plan

Document drafted, posted on project site

document Rob

Friday, Feb. 7

Briefing Report Draft document synthesized from team input document Steve Monday, Feb. 10
         
top
Next Week's Goals

Our goals for next week

  • Complete research, interviews
  • Identify driving issues for project
  • Complete performance analysis and associated documents
  • Plan for next steps
top
Next Week's Meeting

Our next meeting will be held on Thursday, Feb. 6. The following team members will fill the capacity of

Facilitator: Peter Huffer
Scribe: Rob Parrott
Status Reporter: Rob Parrott
top
Remarks/ Concerns

The following concerns need to be addressed

  • Logo for site
  • email protocol
  • Performance Analysis Plan
  • Results of research, interviews
  • Briefing Report
top