LAO Team Weekly Status Report

 
 
Week's Activities | Issues Addressed | Next Week's Goals | Next Week's Meeting | Remarks/Concerns
 
Date April 28 through May 2  
Prepared By Rob Parrott  
Week's Activities

Our team met to discuss the following:

  • Sub-team updates
  • Innovations 2003 final preparations
  • Project manager items
  • Project site updates
top
Issues Addressed
Issues Action to be Taken Deliverable Owner Due Date
Innovations Posters Create posters for Innovations booth plan and documents Liz Wed, 4/30
Read from the Web

Button design and five finger rule

design and edited text Rob

ASAP

Camtasia Videos Think about where to insert Camtasia videos as help on the site and tell Karen feedback Team 5/6
Uploading all project documents Send documents to be uploaded on the project site to Rob or Karen Emails with attachments Team ASAP
Ideas for Final Presentation Think about ideas for presenting at our final feedback Team 5/6
top
Next Week's Goals

Our goals for next week

  • Finish designs
  • Begin preparations for final presentation
top
Next Week's Meeting

Our next meeting will be held on Tuesday, May 6th. The following team members will fill the capacity of

Facilitator: Peter Huffer
Scribe: Rob Parrott
Status Reporter: Rob Parrott
top
Remarks/ Concerns

The following concerns need to be addressed:

All efforts directed toward completing redesign and then final presentations.

top